1. Foundation and chassis installation

First determine the foundation position of the elevator and carry out foundation construction, including digging foundation pits, pouring concrete, etc., to ensure that the foundation meets the load-bearing requirements of the elevator.

Install the chassis in place, pass the anchor bolts through the chassis holes, connect them with the reserved holes of the foundation, use a level to measure and adjust the level of the standard section bottom section butt joint, fill the gap under the chassis, and then tighten the anchor bolts.

2. Fence installation

Connect the side fence to the chassis, connect the rear fence and side fence in turn, then install the power cabinet door frame, and tighten the safety fence bolts.

Use a tower crane to install the outer cage door, pay attention to the selection of lifting points to prevent the outer cage door from deformation, fix all outer cage bolts, install the outer cage counterweight slide, and adjust the entire set of outer cage levels.

Install the outer cage door support and adjust it to the size suitable for hanging the cage, install the buffer spring base, and add the buffer spring.

3. Installation of cage and transmission trolley

Prepare the tower crane and more than 4 staff members to cooperate, lock the balance lock of the cage lifting point, select a suitable lifting environment, and command the tower crane to lift smoothly.

The tower crane will gently swing the cage to the upper part of the outer cage (about 5 meters from the foundation), gently lower it and slowly insert it into the standard section. During the lowering process, pay attention to the position of the cage in all directions, so that it can be safely and steadily placed in the buffer spring. Use the same method to insert the other cage into the standard section, and install and fix the cage top safety fence at the same time.

Prepare the transmission trolley connecting pin and related tools, and check whether the end brake device of the transmission motor is relaxed.

Check the transmission trolley to distinguish the left and right cage transmission devices according to the number, use the crane to smoothly lift the transmission trolley, slowly insert it into the standard section, command the crane to slowly lower it to the pin hole connected to the cage and the transmission trolley, insert the connecting pin, and install the connecting pin to prevent it from exiting from the pin hole, and hoist the other transmission trolley device.

Loosen the bolts of the transmission motor brake device and check whether it is effective, and install the motor rain shield.

4. Guide frame installation

Wipe the pipe joints at both ends of the standard section and the rack pins clean, and add a little grease.

Open a guardrail, lower the hook on the boom, and hook the standard section hoist, hook the standard section hoist to a standard section, crank the hand winch, and lift the standard section to the top of the cage and stabilize it.

Close the guardrail, start the elevator, and when the cage rises to the top of the guide frame, it should be driven until the top of the cage is about 300mm away from the top of the guide frame. Stop, lift the standard section with the boom, align the hook with the pin holes on the standard section riser and rack below, fix it with bolts, loosen the hook, turn the boom back, and tighten all bolts with a tightening torque of 350N·m. In this way, connect the standard sections in sequence until the required height is reached.

As the guide rail frame is continuously raised, the wall frame should be installed at the same time, and the verticality of the guide rail frame installation should be checked.

5. Wall frame installation

When the installation height of the guide rail frame of the elevator is close to 6 meters, the first set of attachment devices should be installed. The height of the attachment frame from the ground is 4 to 9 meters (it can also be determined according to the specific situation). The maximum height of one attachment frame shall not exceed 7.5 meters, and the distance between two adjacent attachment frames shall not be greater than 9 meters. When installing the wall-mounted system, it should be required to be carried out during the cage top operation. The installation of the wall-mounted system and the addition of the guide rail frame should be carried out simultaneously.

6. Electrical system installation

Connect the power supply cable from the main power switch in the power box on the elevator to the on-site power supply box.

Coil the cable into the cable cage in a free state. One end of the cable is led out from the bottom of the cable cage to the power box, and the other end is led into the cage through the cable bracket to the electric control box.

The cable cage is installed below the cable bracket so that the cable is in its center and can be freely pulled out or coiled into the cable cage.

After completing the above assembly steps, the construction elevator needs to be fully inspected and debugged, including electrical device inspection, installation and debugging of limit switches and limit switch contact irons, etc., to ensure that each component is installed correctly and operates normally, and all safety indicators meet the requirements before it can be put into use.

 

Website: HTTPS://WWW.SHENXI.COM

Follow us on: HTTPS://WWW.FACEBOOK.COM/SHENXI.EXPORT

My Blog: HTTPS://WWW.SHENXI.COM/NEWS/LIST

SubscribetomyYouTube:HTTPS://WWW.YOUTUBE.COM/SHENXIMACHINR

Get Your FREE Quote

Get Your FREE Quote

We will contact you within 24 hours.